I just really want to double check that what I am about to do wont break everything.
I have a 2 node Hyper-V 2008R2 cluster, with 15 VM's).
I have purchased a 3rd server where I will install Server 2012R2 and Hyper-v.
the idea build 1 server and connect up to the Shared storage. Shut down all VM's
Import them into the New Hyper-V server
Break the old cluster, rebuild server to 2012R2 and create highly available cluster. power on the VM's.
rebuild final server to 2012R2 and then have a 3 node cluster.
Does this seem correct in terms of order or should I switch around any steps